Uganda's army chief says the Yapi Merkezi railway contract is cancelled, two weeks after he approved it

Gen Muhoozi Kainerugaba said on Saturday that Uganda had ended the Turkish builder's role in the 272 km Malaba to Kampala line, a contract worth about $2.97 billion. He gave no reason, and the works ministry had not confirmed a formal termination.

The Kampala skyline at dusk, with towers beyond a green field and a dirt path
File photo: Kampala, 17 April 2010 (cropped); the railway route is not shown. Photo: Todd Huffman / Wikimedia Commons, CC BY 2.0

Uganda's Chief of Defence Forces, Gen Muhoozi Kainerugaba, said on Saturday that the government had cancelled its contract with Turkish construction company Yapi Merkezi to build the first phase of the Standard Gauge Railway, two weeks after he publicly approved the same company to do the work.

"We have cancelled the SGR contract with the Turkish company Yapi Merkezi indefinitely. We shall find a more suitable and effective partner soon," Muhoozi, who is President Yoweri Museveni's son, wrote on X. He did not give a reason or name a replacement contractor.

The Ministry of Works and Transport had not publicly confirmed a formal termination of the agreement, The Eastleigh Voice reported. No public response from Yapi Merkezi had been reported by Sunday morning.

A contract that keeps changing hands

Uganda signed the construction agreement with Yapi Merkezi on 14 October 2024. It is worth 2.7 billion euros, about $2.97 billion, and covers 272 km of railway from Malaba on the Kenyan border to Kampala, through Tororo, Iganga, Jinja and Mukono. Museveni launched construction in Tororo on 21 November 2024, with a 48-month build period. The deal replaced an earlier arrangement with China Harbour Engineering Company, which collapsed after the Chinese firm failed to secure financing.

Saturday's post is the second time this year that Muhoozi has announced the contract's end. On 16 June he said it had been cancelled and called on supporters of the Patriotic League of Uganda, the political organisation he chairs, to demonstrate outside the Turkish embassy, Uganda Radio Network reported. The ministry did not confirm that cancellation either. On 6 November he reversed course: "Under the direction and instructions of Mzee Museveni, I approve the Turkish company Yapi Merkezi to implement the 1st Phase of the SGR. From Malaba to Kampala."

Financing still being assembled

Full construction depends on financing that has not yet closed. The government appointed Citibank in April to help raise money for the project, and the Islamic Development Bank approved about $715 million in June for bridges, tunnels, stations and maintenance facilities. The OPEC Fund for International Development was reported to be considering a loan of about $165 million.

Works and Transport Minister Fred Byamukama had told Parliament that the government was aiming for financial close in January 2027. Until then, Yapi Merkezi has carried out preparatory works under a limited notice to proceed worth about $82 million, according to the ministry's account to Parliament reported by Eagle Online. The government said on 18 November that it had paid compensation to 7,721 people affected by the route, with another 5,225 still waiting.

The Malaba to Kampala line is the first leg of a planned 1,700 km network meant to link Uganda to Kenya's railway and the port of Mombasa, with later branches towards South Sudan, the Democratic Republic of Congo and Rwanda. The government has not said how the cancellation will be carried out or when a new contractor might be chosen.

SourcesShow
  1. Eagle Online, "Gen Muhoozi terminates Shs10.8t SGR deal with Turkish firm Yapi Merkezi", 21 Nov 2026. https://eagle.co.ug/2026/11/21/gen-muhoozi-terminates-shs10-8t-sgr-deal-with-turkish-firm-yapi-merkezi/
  2. The Eastleigh Voice, "Muhoozi announces cancellation of Sh385 billion SGR contract with Turkish firm", 21 Nov 2026. https://eastleighvoice.co.ke/news/426488/muhoozi-announces-cancellation-of-sh385-billion-sgr-contract-with-turkish-firm
  3. Uganda Radio Network, "Museveni Directs SGR Works to Proceed", Nov 2026. https://ugandaradionetwork.com/s/museveni-directs-sgr-works-to-proceed/
  4. Kenyans.co.ke, "Uganda Cancels Multi-Billion SGR Deal With Turkish Firm, Muhoozi Claims", 21 Nov 2026. https://www.kenyans.co.ke/news/129568-uganda-cancels-multi-billion-sgr-deal-turkish-firm-muhoozi-claims
  5. European Central Bank, euro foreign exchange reference rates, 20 Nov 2026 (used for dollar conversions). https://www.ecb.europa.eu/stats/policy_and_exchange_rates/euro_reference_exchange_rates/html/index.en.html